Substation 110/35/6 kV Kuryazh

In 2021, our company supplied equipment for Outdoor SWG-110 kV manufactured by GE and TRENCH for the contractor PSK Energobud LLC, which signed a contract for the performance of work with KHARKIVOBLENERGO JSC

Reconstruction of the Substation 35/6 kV Kuryazh in terms of transferring the substation to voltage 110/35/10/6 kV, installation of Power transformer T-4 110/35/10 kV and the necessary equipment. The need to reconstruct the substation arose in connection with the increase in electricity consumption by the population and industrial enterprises located near this power facility.

Increasing the voltage class of the Kuryazh substation will reduce electricity losses, maintain the voltage level and load on the network elements in acceptable values.

SF6 Live Tank Circuit Breaker 145 kV GL312 F1/4031 P - 1 pcs

Current transformer 126 kV IOSK 123 with paper-oil insulation - 3 pcs